Road to public launch — the 9 months before Africnam goes live
A month-by-month countdown of the regulatory, technical and commercial milestones between today and Africnam's public launch across 26 African markets.
Africnam is today in controlled pilot mode. Public availability across our 26 African markets is scheduled for T+9 months. Below is the transparent countdown, so ministries, insurers, telcos and pharmacies know exactly what is being built, when, and by whom.
- M-9Sovereign hardening
ISO 27001 gap closure, in-country data residency contracts, third-party pentest kick-off.
- M-8Payments live rails
Onafriq production keys, 90/10 automated split, USD escrow with a Tier-1 correspondent bank.
- M-7Telco integration
Production USSD short-codes negotiated with 3 lead MNOs, SMS OTP fallback certified.
- M-6Regulatory greenlights
Health-ministry MoUs signed in lead markets (Uganda, Kenya, DRC), insurance sandbox approvals filed.
- M-5Clinic & pharmacy onboarding
500 clinics + 1,200 pharmacies pre-enrolled through local BD teams, OTP dispensation training completed.
- M-4Mobile apps in stores
iOS App Store and Google Play submissions cleared, beta channels opened to 10,000 users.
- M-324/7 SOC + SRE
Security Operations Centre and Site Reliability team on rotation, on-call runbooks rehearsed.
- M-2Public reference customers
First 3 corporate B2B contracts announced, national monitoring dashboards handed to ministries.
- M-1Load & red-team
Peak-load simulation at 10× target volume, external red-team exercise, public bug-bounty opened.
- M-0Public launch
Africnam opens to the general public across lead markets. Progressive rollout to the remaining 23 countries over the following two quarters.
Each gate is owned by a named workstream lead and gated by measurable KPIs — no gate, no launch. The full RACI and technical playbook are shared under NDA with government partners on request.